Ongoing Projects

Major water supply and sewerage projects under execution by the Board.

  • Sustainable Water Supply
  • Stronger Infrastructure
  • Better Service for Hyderabad
  • Healthier Communities
  1. 1/3Work in Progress

    Godavari Drinking Water Supply Scheme Phase-II & III

    Filling of Osmansagar and Himayathsagar reservoirs with Godavari water for the rejuvenation of the Musi river. HAM project — 60% agency, 40% Government of Telangana.

    G.O.Rt.No.30, MA&UD (Engg.) Dept., dt. 25.01.2025

    ₹ 7360.00 Cr.Project Cost
    Date of Agreement
    18.09.2025
    Scope
    3000/2400/2200 mm dia MS pipe — 37 km manufactured and 18 km laid. WTPs, reservoirs and pump houses under construction.
    Target Completion
    December 2027
    Remarks
    Lr. addressed to GoI, MoHUA vide 897563/UBS/2026, dated 21.02.2026, for 25% grant under UCE. Right of way required from R&B Dept. for laying the pipeline from Ghanur to Muneerabad X roads (7 km).
    1. Planning
    2. Procurement
    3. Execution (current stage)
    4. Completion
  2. Under Tender Process

    Manjeera Phase 1 & 2 Refurbishment / New Line

    40 MGD of additional water supply to be added to the city.

    G.O.Rt.No.315, dt. 05.03.2026

    ₹ 722.00 Cr.Project Cost
    Date of Agreement
    —
    Scope
    Under tender process
    Target Completion
    —
    Remarks
    —
    1. Planning (current stage)
    2. Procurement
    3. Execution
    4. Completion
  3. Procurement

    Osman Sagar and Himayat Sagar Optimization

    27 MGD of additional water supply to be added to the city.

    G.O.Rt.No.316, dt. 05.03.2026

    ₹ 282.00 Cr.Project Cost
    Date of Agreement
    —
    Scope
    Work order issued
    Target Completion
    —
    Remarks
    —
    1. Planning
    2. Procurement (current stage)
    3. Execution
    4. Completion
  4. 1/3Work in Progress

    Neopolis Water Supply Trunk Main, Pumping Station and 45 MLD STP

    G.O.Rt.No.123, MA&UD (Engg.2) Dept., dt. 12.03.2025

    ₹ 298.00 Cr.Project Cost
    Date of Agreement
    06.02.2026
    Scope
    Two 2.5 ML ELSRs under construction. 1800/1500 mm dia MS pipes — 3.0 km fabricated, 1 km laid.
    Target Completion
    January 2028
    Remarks
    With HMDA funds
    1. Planning
    2. Procurement
    3. Execution (current stage)
    4. Completion
  5. 1/2Work in Progress

    Intake Structure and Pumping Station at Sunkishala

    Electro-mechanical works and transmission mains from Sunkishala to Kodandapur WTP, including manning, operation and maintenance for 24 months.

    G.O.Rt.No.238, dt. 16.03.2021 · G.O.Rt.No.720, dt. 09.11.2022

    ₹ 2214.76 Cr.Project Cost
    Date of Agreement
    11.06.2021
    Scope
    Intake well and pump house 70% complete. Electro-mechanical component 90% complete. Three rows of 2375 mm dia MS pipeline 88.4% laid.
    Target Completion
    —
    Remarks
    —
    1. Planning
    2. Procurement
    3. Execution (current stage)
    4. Completion
  6. Work in Progress

    5 ML GLSR at Mahendra Hills

    G.O.Rt.No.294, dt. 20.06.2025

    ₹ 14.95 Cr.Project Cost
    Date of Agreement
    06.02.2026
    Scope
    Retaining wall under construction
    Target Completion
    —
    Remarks
    —
    1. Planning
    2. Procurement
    3. Execution (current stage)
    4. Completion
  7. Work in Progress

    7 ML GLSR and 2 ML ELSR at Asmangadh

    G.O.Rt.No.294, dt. 20.06.2025 · G.O.Rt.No.518, dt. 05.05.2026

    ₹ 16.00 Cr.Project Cost
    Date of Agreement
    08.05.2026
    Scope
    Preliminary works and structural designs in progress
    Target Completion
    —
    Remarks
    —
    1. Planning
    2. Procurement
    3. Execution (current stage)
    4. Completion
  8. Work in Progress

    Water Supply Master Plan

    For the HMWSSB water supply area, extending to the Telangana Core Urban Region economy.

    ₹ 12.85 Cr.Project Cost
    Date of Agreement
    —
    Scope
    Draft inspection report
    Target Completion
    —
    Remarks
    —
    1. Planning
    2. Procurement
    3. Execution (current stage)
    4. Completion
  9. Under Tender Process

    Water Supply Infrastructure — Bandlaguda

    Three reservoirs and MS/DI inlet, outlet and distribution mains for six new colonies in the Bandlaguda area of Chandrayangutta Assembly Constituency.

    ₹ 50.00 Cr.Project Cost
    Date of Agreement
    —
    Scope
    Tender stage
    Target Completion
    —
    Remarks
    —
    1. Planning (current stage)
    2. Procurement
    3. Execution
    4. Completion
  10. Under Tender Process

    Water Supply Infrastructure — Cantonment

    Sump, pump house, pumps and motors, a 2.5 ML ELSR at Gun Rock, Teachers Colony, a 6 ML GLSR at Risala Bazar, and MS/DI inlet and outlet connections in Cantonment Constituency.

    ₹ 32.00 Cr.Project Cost
    Date of Agreement
    —
    Scope
    Tender stage
    Target Completion
    —
    Remarks
    —
    1. Planning (current stage)
    2. Procurement
    3. Execution
    4. Completion
  11. Under Tender Process

    Refurbishment of Manjeera Water Supply Scheme Phase-I & Phase-II

    With Government budgetary support to HMWSSB, for implementation over two years.

    G.O.Rt.No.315, dt. 05.03.2026

    ₹ 722.00 Cr.Project Cost
    Date of Agreement
    —
    Scope
    Tender stage
    Target Completion
    —
    Remarks
    —
    1. Planning (current stage)
    2. Procurement
    3. Execution
    4. Completion
  12. Work in Progress

    Butterfly Valves and Non-Slam Check Valves for Transmission Pumping Stations

    600/700 mm dia butterfly valves and 600 mm dia non-slam nozzle check valves for the 1300/1475/1425 KW pump sets at the 6.6 KV Phase-I, II and III pumping stations at Kodandapur, Nasarlapally and Godakondla, and a 2000 mm dia butterfly valve on the 2200 mm dia MS pumping main of KDWSP Phase-I at Nasarlapally.

    ₹ 22.00 Cr.Project Cost
    Date of Agreement
    —
    Scope
    Work in progress
    Target Completion
    —
    Remarks
    Electrical Sub Division SD-IV, Transmission Division No.III, Sahebnagar
    1. Planning
    2. Procurement
    3. Execution (current stage)
    4. Completion
  13. Under Tender Process

    Flood Protection for Pump Houses and 132/6.6 KV Sub Station, Peddapur

    Slice-I from 0.000 to 0.260 km, Slice-II from 0.261 to 0.510 km and Slice-III from 0.511 to 0.750 km at Peddapur campus.

    ₹ 13.50 Cr.Project Cost
    Date of Agreement
    —
    Scope
    Government approval accorded
    Target Completion
    —
    Remarks
    SD-II, Transmission Division II, Patancheruvu
    1. Planning (current stage)
    2. Procurement
    3. Execution
    4. Completion
  14. Under Tender Process

    Repairs to the Flexible Apron at the Energy Dissipater, Manjira Barrage

    Downstream of the Manjira barrage.

    ₹ 14.20 Cr.Project Cost
    Date of Agreement
    —
    Scope
    Government approval accorded
    Target Completion
    —
    Remarks
    EAM Cell-I, Transmission Division No.II, Patancheru
    1. Planning (current stage)
    2. Procurement
    3. Execution
    4. Completion
  15. Work in Progress

    1 STP in PPP Mode and 38 STPs in HAM Mode for ULBs in the ORR Area

    Under AMRUT 2.0, Tranche-III.

    G.O.Rt.No.344, MA&UD (Engg.2) Dept., dt. 03.08.2024

    ₹ 3849.10 Cr.Project Cost
    Date of Agreement
    07.10.2025
    Scope
    Works in progress. Of 16 STPs, 14 taken up (2 cascaded) — 13 under construction and 1 in a court case. Of 22 STPs, 14 taken up (8 flows cascaded) — 10 under construction and 4 in court cases. One 7 MLD STP in PPP mode.
    Target Completion
    —
    Remarks
    —
    1. Planning
    2. Procurement
    3. Execution (current stage)
    4. Completion
  16. Work in Progress

    Zone-II Sewerage Network, Chandrayangutta Constituency

    Laying of a 156 km network.

    G.O.Rt.No.21, dt. 13.01.2022

    ₹ 301.00 Cr.Project Cost
    Date of Agreement
    27.01.2025
    Scope
    53 km of pipeline network completed
    Target Completion
    —
    Remarks
    —
    1. Planning
    2. Procurement
    3. Execution (current stage)
    4. Completion
  17. Work in Progress

    Four STPs for the Abatement of Pollution in Osmansagar and Himayatsagar

    G.O.Rt.No.244, dt. 20.04.2023

    ₹ 82.23 Cr.Project Cost
    Date of Agreement
    30.01.2025
    Scope
    80% of the work completed
    Target Completion
    —
    Remarks
    —
    1. Planning
    2. Procurement
    3. Execution (current stage)
    4. Completion
  18. Work in Progress

    RCC and SWG Pipelines at Karwan, Nampally and Goshamahal

    G.O.No.06, dt. 02.01.2026

    ₹ 63.50 Cr.Project Cost
    Date of Agreement
    30.05.2026
    Scope
    Work in progress
    Target Completion
    —
    Remarks
    —
    1. Planning
    2. Procurement
    3. Execution (current stage)
    4. Completion
  19. Under Tender Process

    RCC Trunk Sewer Mains, Malakpet Constituency

    G.O.Rt.No.406, dt. 04.04.2026

    ₹ 50.00 Cr.Project Cost
    Date of Agreement
    —
    Scope
    Tender stage
    Target Completion
    —
    Remarks
    —
    1. Planning (current stage)
    2. Procurement
    3. Execution
    4. Completion
  20. Procurement

    In-situ Rehabilitation of the 1600/1800 mm dia Trunk Sewer Main (Duplicate A Main)

    From Divyashakti Apartments to the 20 MLD STP at Hussain Sagar lake, using a trenchless structural lining system.

    G.O.No.173, dt. 10.02.2026

    ₹ 91.00 Cr.Project Cost
    Date of Agreement
    —
    Scope
    Awaiting Government approval for issue of LOA
    Target Completion
    —
    Remarks
    —
    1. Planning
    2. Procurement (current stage)
    3. Execution
    4. Completion
  21. Work in Progress

    Sewer Improvements on the B-91 Sewer Main

    Sewerage gaps closed with 1200/1400 mm dia RCC pipeline from Ranga Mahal to Bagga Wines, and from MJ Market to Darul Salam, Aghapura.

    G.O.No.971, dt. 31.12.2025

    ₹ 57.60 Cr.Project Cost
    Date of Agreement
    —
    Scope
    Work in progress
    Target Completion
    —
    Remarks
    —
    1. Planning
    2. Procurement
    3. Execution (current stage)
    4. Completion
  22. Work in Progress

    Sewerage Master Plan Detailed Project Report for the Telangana Core Urban Region

    G.O.Rt.No.344, dt. 24.03.2026

    ₹ 5.76 Cr.Project Cost
    Date of Agreement
    —
    Scope
    Work awarded; DPR under preparation
    Target Completion
    —
    Remarks
    —
    1. Planning
    2. Procurement
    3. Execution (current stage)
    4. Completion